Project History
Construction Plans are being finalized for the Greene Street streetscape and two-way conversion project. A public meeting was held on January 2019 to provide opportunity for the public to review the plans and provide input.
Two-way conversion recommendations:
- Two lanes southbound
- One lane northbound
- Traffic signal modifications
- Parking deck modifications
Streetscape Features:
- Sidewalk bulbouts at intersections
- Decorative crosswalks
- New sidewalk, curb and gutter
- Sidewalk bulbouts with tree wells
Anticipated Schedule
- Public Meeting - January 2019
- Complete Construction Drawings - Spring 2022
- Begin Construction - Spring 2024
- End Construction - Late 2024